Client

Engie

Starting year

2019

End date

01/12/2021

Technical inspection of works | The wind farm has an installed capacity of 151 MW and consists of 36 wind turbines. The civil works for the project include the foundations for the wind turbines, internal roads, assembly platforms, and trenches for medium-voltage cables. The energy generated will be fed into the National Electric System through a 33/220 kV step-up substation